| First Floor
17. Floodproofing
Ordinarily a building such
as this, located in a flood plain and undergoing such extensive renovation,
would have to be elevated at a level above Base Flood Elevation (BFE) in
order to qualify for flood insurance coverage under the National Flood
Insurance Program (NFIP). BFE is an estimate of the water level from
a flood with a one percent chance of occurring in any given year.
However, because this house
is located in an historic district, the rules are slightly different.
In an historic district, if elevating a structure would harm its historic
character, the elevation requirement may be waived. This is exactly
what happened in this case. Because the building couldn’t be elevated
to BFE, other measures, known as “wet flood proofing”, were taken.
As mentioned below (see Foundation
and Insulation) the house was partially elevated to keep it above the threat
of small flood events without harming its historic character. It
was also insulated with non-water absorbing foam insulation under the first
floor. Several additional floodproofing elements can be seen on the
first floor of the building.
All electric, telephone
and computer outlets have been located above BFE. In addition, there
are no splices or connections below BFE. So if a major flood event
does occur damage to the electrical system of the house will be absent
or minimal.
Wainscoting
On the first floor notice
that wooden panels, called wainscoting, have been installed to approximately
BFE. These panels are less water-absorbent than is wallboard and
can be removed after a flood event, allowing both the panels and the wall
space to dry thoroughly. Wallboard absorbs water, which then wicks
upward damaging walls to a level well above the actual flood level.
Insulation
There are three kinds
of insulation used in the house. Modern homes have well insulated
exterior walls, roofs and floors. The first floor is insulated with
solid foam panels that fit in between the floor joists. This material
was selected in place of the more usual fiberglass batts as a part of the
wet-floodproofing design. If there were a flood and the foam insulation
were torn from under the floor, it could be recovered and re-installed
because it doesn’t absorb water. As under the floor, the wall insulation
on the first floor below BFE consists of solid foam, non-water-absorbing
panels. Above the foam, blocking has been installed to create a physical
barrier to prevent water from damaging the insulation above.
In the walls above base flood
level in the first floor walls, in the second and third floor walls, a
relatively new insulation material has been used – cellulose. Cellulose
insulation is essentially ground up newspaper, treated with boric acid
for fire retardation and insect resistance. An adhesive is also added
so that it can literally be blown into vertical wall spaces without appreciable
settling. This insulation can be seen in a demonstration panel on
the first floor and in a much larger area on the third floor. Research
done at the University of Colorado has shown that cellulose outperforms
fiberglass, reducing energy consumption by 26% to 38%. Cellulose
also has much better air-penetration resistance than fiberglass because
of its higher density. This contributes to its nearly 50% greater
efficiency than fiberglass at very low temperatures. Its use contributes
to reduction of waste from old newspapers and other paper going into landfills.
Production and energy costs are also substantially lower than for fiberglass
insulation.
Traditional fiberglass batts
have been used between the roof rafters and can be seen at the exposed
edge of the sheet rocked ceiling along the east wall on the third floor.
HVAC System
Note also that the HVAC
unit and returns are located above BFE. Also, the duct work has been
installed at ceiling height to prevent flood damage. See 22.,
Geothermal Heating and Cooling System, for more information about the
HVAC system.
18. Fireplace
The original fireplace and
chimney were badly deteriorated and collapsed in the process of elevating
the house. Like most fireplaces and chimneys, the originals were
non-reinforced, meaning they were constructed of brick and mortar alone,
with no steel reinforcing bars. This lack of reinforcement makes
them very dangerous in earthquakes and hurricanes. The force of shaking
in an earthquake or the force of the wind can cause non-reinforced masonry
to collapse. It is very difficult to make a masonry fireplace and
chimney safe from these hazards.
There are however things that
can be done to make fireplaces and chimneys safer. Here you can see
a special cement flue liner that can be built-in to new chimneys or retrofit
into existing ones to provide additional strength to the structure and
help hold it together when shaken by earthquakes or blown by hurricane
winds. The liner fills cracks in the chimney and replaces old mortar.
Another option for an existing
chimney could be to “frame-in” an interior masonry chimney. By creating
a box around the chimney, if it were to collapse, it would collapse within
the framing. It is also possible to fill the entire chimney with
a cement grout, making it non-functional, but safer. Any of these
efforts represents a compromise, since it is safest not to have an non-reinforced
brick fireplace and chimney in a seismic zone, like Charleston.
19. Foundation
The original foundation at
113 Calhoun was "brick on dirt"—non-reinforced brick laid on a compressed
earth footing buried about three feet in the ground. Due to the extreme
deterioration of the original foundation, it was completely replaced in
the course of renovation. Detailed
drawings of the foundation before and after renovation are available.
The
new foundation consists of a concrete footing reinforced with steel rods.
On the footing concrete block replaced the original brick. The block
was filled with a concrete grout into which threaded steel rods were anchored.
These rods allowed the new timber “sills” to be bolted onto the foundation.
This retrofit provides the building with greater resistance to shaking
and twisting from earthquake and wind forces, as well as preventing it
from floating off its foundation in a severe flood.
The original brick from the
foundation was re-used as a veneer over the concrete block to preserve
the original look of the building in keeping with its historic character,
and
conserving resources through their re-use.
In
the course of re-building the foundation, the building was elevated by
about one foot. This small elevation produced a great benefit in
flood protection. The house is located in a flood plain. It’s
first floor elevation is almost four feet below “Base Flood Elevation”,
a measure of flood vulnerability. Clemson University Civil Engineers
calculated that by raising the building just a foot, it would be high enough
to protect it from the more numerous minor flooding events. The elevated
building is now susceptible only to larger, less frequent flood events,
reducing the probability of flood damage by about 60%.
Notice here the block
foundation and the brick veneer. See how the foundation is bolted
to the wood house-framing member. This solid connection not only
prevents the house from shaking or floating off its foundation, it provides
the basis for a “continuous load path” that connects the house from foundation
to roof.
20. Continuous Load Path
“Continuous load path”
is an engineering term that refers to a series of connections that allows
forces, such as those created by shaking in an earthquake, to pass from
one part of a structure to another and allow the building to move as a
unit. Without a continuous load path, there are “weak links” in a
building’s connections. Those weak spots are where failures are most
likely to occur. In an earthquake, for example, it would do little
good to reinforce the connections in the building’s framing if the framing
isn’t connected to the foundation. In such a case, the house may
not fall apart, just shake off the foundation.
In this building, the poured
concrete footing forms a solid connection between the ground and the concrete
block foundation. The foundation is bolted to the wood framing, which
is tied together with metal connectors from the first floor to the third.
Finally, the walls are connected to the roof with metal connectors called
“hurricane clips”. These links form the building’s continuous load
path.
21. High Wind Bracket
The High Wind Bracket,
invented by a graduate student researcher at the Clemson University Department
of Civil Engineering, is a sturdy aluminum extrusion used to improve a
building's connections. Here, it secures a portion of the second
floor to the first floor wall. The bracket provides an alternative
to removing a home's wallboard and installing metal clips. It is
simply lag screwed to individual framing members—in this case, the upper
story floor joists and lower story walls—and covered with a bold cornice.
The bracket can be installed in various locations, most commonly to the
roof truss and walls to secure the roof. The bracket also resists
damage from tree fall—tests at Clemson University show it to stop the descent
of a 10-inch diameter pine.
Interior Water Use
Because of space limitations,
the house has no kitchen or laundry to demonstrate some of the more significant
water and energy conservation measures that can be taken in the typical
home. In this house these aspects of energy and water conservation
are limited to a “low flow” 1.6 gallon per flush toilet and a “point of
use” water heater. Unlike a typical tank-type water heater, the “point-of-use”
water heater, located just below the sink in the bathroom, heats water
only as it is needed. It prevents the need for continually re-heating
excess water in a storage tank. It also eliminates the waste of water
that sits in the hot water line between a central water heater and the
faucet, which cools between uses. |
22.
Geothermal Heating and Cooling System
There are many methods
now in use in the Charleston area to heat and cool homes. Most of
them use energy from electricity, natural or propane gas, or fuel oil to
heat or cool the air that circulates throughout the house. Geothermal
“heat pump” systems use the temperature of the soil as its energy source.
Although not in common use at this time, geothermal systems are among the
most energy-efficient systems available.
A typical heat pump found in
many homes extracts heat from the air outdoors in winter and brings it
into the house for warming. In summer it extracts heat from the air
inside the house and vents it outdoors. The geothermal heat pump
works in the same way, only instead of an air-to-air heat exchange, it
uses a system of buried plastic pipes circulating water to exchange heat
with the earth.
The system consists of an indoor
heat exchanger, an underground water circulation system and a zoned air
distribution duct system. By having the heat exchanger housed indoors,
weather-related deterioration is eliminated, thus extending its useful
life. Almost twenty-five hundred feet of 3/4-inch plastic pipe, with
high heat transfer qualities, is buried under the landscaping and connected
to the heat exchanger. This closed-loop piping is buried in six 200
- foot deep by 4 - inch diameter wells dug along the back yard fence.
In Charleston, the ground temperature, below three feet, is approximately
68 degrees year around. In the winter, heat is transferred from the
ground to warm the house. In the summer, heat is transferred from
the house to the ground thus cooling the house.
Inside the house, heated
or cooled air is distributed to the rooms through a zoned duct system.
Note that on the first floor, as a part of the flood proofing of the house,
the ductwork and return are located at ceiling level. All the ductwork
in the house has interior insulation to keep the air hot or cold as it
moves through the ductwork. On the third floor, the ductwork is also
insulated on the exterior due to high heat levels adjacent to the non-insulated
part of the roof. (Leaving the roof non-insulated was a compromise
dictated by the need to demonstrate roof hazard retrofit.)
The air distribution system
consists of three zones, controlled by thermostats on each floor.
The system works with a series of electric controlled dampers that control
the amount of air going to each zone.
In most homes, perhaps the
greatest waste of energy occurs when heated or cooled air is distributed
to rooms that are not in use. Much of this waste can now be eliminated
by the use of programmable thermostats, that can heat or cool an individual
zone at four to six separate settings per day, seven days per week, summer
and winter.
23,
24 and 25. Windows/Glazing
Windows and doors, along
with the roof and siding form what engineers call the “building envelope”.
This “envelope” is the building’s skin and serves as a barrier to things,
such as rain, entering the building, and leaving the building, such as
heat. If for example, windows are broken in a hurricane, rainwater
may enter the house damaging or destroying its contents. Likewise,
if the windows don’t effectively hold heat inside the building, heating
costs will go up and resources will be wasted.
At
113 Calhoun St. several types of windows have been used in order to demonstrate
the range of available windows and how they perform as components of the
building envelope. In the first floor office and on the porch doors
on both floors the original windows of the house were re-used for consistency
with Board of Architectural Review (BAR) guidance governing buildings in
the historic district. The office windows [23] are single pane, “six
over six”, true divided light windows, and are neither very storm resistant
nor energy efficient. Their lack of storm resistance is compensated
for by hurricane shutters, as is discussed elsewhere. To compensate
for their energy inefficiency, interior acrylic insulating panels [23]
held in place by magnetic frames have been installed in the first and third
floor offices. These panels function as interior “storm” windows
and increase the energy efficiency of the windows substantially.
Heat loss in BTU’s is reduced by 77 % from 260 to 60. These interior
panels are consistent with BAR requirements in the historic district, but
may also be useful in non-historic home and business applications.
In fact, the panels have been used to cover the exposed wall on the east
wall of the building (left open to show the building framing and connectors)
to improve energy efficiency there.
Throughout the rest of the
house double-pane “thermal” glazing has been used [24]. This type
of glazing, more energy efficient than the single pane, has been used in
double hung, single hung and casement window frames of wood and vinyl cladding.
The casement window on the second floor has a window film applied over
the glass to improve the “R” value of the window [25]. Window film
is marketed to homeowners for increased energy efficiency as well as hurricane
protection. While window film will likely hold together pieces of
shattered glass in a hurricane situation, it is unlikely to be effective
in preventing a breach in the building envelope in hurricane force winds.
Here on the optional video clips,
I'll take you inside the building at 113 Calhoun Street, where you will
meet the 113 Calhoun Street Program Coordinator, Dick
Dalla Mura. You'll also see how we've strengthened the walls,
and what kind of insulation we use in the building.
1. Enter
and Meet Mr. Dalla Mura (392 KB)
2. Main
Room and Chimney (328 KB)
3. First
Floor: Building Connections (669 KB)
4. Head
Upstairs (128 KB)
Now let's head on up to the
Second
Floor.
|